● Schedule development can require the review and revision of duration estimates and resou
11 查阅
● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.
(74)
A.scope statement
B.activity list
C.project charter
D.project schedule
参考答案: