Schedule development can require the review and revision of duration estimates and resou

14 查阅

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule

参考答案:

D制定进度表可能要求对历时估算与资源估算进行审查与修改,以便进度表在批准之后能够当做跟踪项目绩效的基准使用。

软考中级