● In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project' s communications. According to Metcalfe's Law, a project with 10 stakeholders has ( 73 ) potential communication channels.

(73) A. 10

B. 45

C. 50

D. 100

参考答案:

B