Estimate activity durations is the processof estimating the number of work periods to comp

14 查阅

Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

A.expert judgment

B.analogous estimating

C.requiremen tstraceability matrix

D.three-point estimating

参考答案:

C