The(  )provides the project manager wi

14 查阅

问题:

[单选] The(  )provides the project manager with the authority to apply organizational resources to project activities。

A . project management plan

B . project charter

C . project human resource plan

D . project stakeholders

参考答案:

B

项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。