After calculating both the simple payback period and the discounted payback period for a project, th

6 查阅

After calculating both the simple payback period and the discounted payback period for a project, the discounted payback period is:()计算一个项目的静态投资回收期和动态投资回收期后,动态投资回收期为:()

A.shorter because the time value of money raises the value of the cash flows.更短,因为货币的时间价值提高了现金流的价值

B.longer because the time value of money raises the value of the cash flows.更长,因为货币的时间价值提高了现金流的价值

C.shorter because the time value of money lowers the value of the cash flows.更短,因为货币的时间价值降低了现金流的价值

D.longer because the time value of money lowers the value of the cash flows.更长,因为货币的时间价值降低了现金流的价值。

参考答案:

答案:longer because the time value of money lowers the value of the cash flows.更长,因为货币的时间价值降低了现金流的价值。