Theearnedvaluetechniqueisacommonlyusedmethodofperformancemeasurement.Itintegratesprojectscope,schedu

18 查阅

A、the cost savings for work completed

B、the project is ahead of its planned schedule

C、the cost overrun for work completed

D、less work was completed than was planned

参考答案:

C

挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、 进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CP1=EV/AC) 值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

信息系统项目管理师