is a method used in Critical Path Methodology for constructing a project schedule ne
17 查阅
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them. A.PERT B.AOA C.WBS D.PDM
参考答案: