The Estimate Activity Resource process is closely coordinated with the(73)process.
11 查阅
The Estimate Activity Resource process is closely coordinated with the(73)process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
参考答案: