The Estimate Activity Resource process is closely coordinated with the(73)process.

11 查阅

The Estimate Activity Resource process is closely coordinated with the(73)process.

A.Estimate Costs

B.Sequence Activities

C.Plan Communications

D.Conduct Procurements

参考答案:

A解析:估算活动资源与成本估算是密切联系的。