● Many useful tools and techniques are used in developing schedule. (72) is a schedule net
23 查阅
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
(72)
A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain method
参考答案: