Theprojectmanagermustmaintainaneffectivecommunicationlinkwiththecustomer’ssatisfactionwiththeprogres
17 查阅
A、Periodic project reports, periodic visits to the customer, and telephonic exchanges
B、Subordinates, project team members, and the project sponsor
C、One-time reports, weekly reports, and monthely reports
D、The telephone, facsimile, and data transmission
参考答案: